Challenger 2 MBT - Technical data and Discussion (Part 1)

No idea how lol
If I can, I don’t see an option.

Only if you catch them just after deletion, once it deloads it is a lost cause

Ok, i just checked, it seems like the post deloads instantly, that was not the case untill now, so you cant restore it, but you do it with retry button

Did you not make a report of the same thing already? Just c+p from there?

Restored.

13 Likes

-Updated version for clearer wording and explanation:

CHALLENGEER 2 PLATE APPROXIMATION [REUPLOAD]

SECTION 1: SPECIFICATIONS AND BASELINE VALUES
Challenger 2 base model weight = 62.5t
Challenger 2 TES/OES = 74.8t
TES total mass = 74.8 - 62.5 = 12.3t

Challenger 2 dimensions (approximate):
Length = 8.3 Meters
Width = 3.5 Meters
Height = 2.5 Meters

SECTION 2: STEEL PLATE THEORY


Base plate is roughly 3/4 the height of the hull if laid flat on the floor.
Shaving off 0.5 meters for the turret, and reducing to 3/4s we are given a height of 1.5 meters in height for the base plate.
The length of the plate can be measured as roughly 3/4 the length of the vehicle. 6.2 meters.
The thickness of the plate is known to be 40mm as seen in te screenshot above.

Therefore, for our total mass calculation, we will be using a theoretical steel plate that is 6.2 by 1.5 by 0.04
By using the formula Weight = Area x Thickness x Density, we are given the total weight of our approximated base plate.
Area = Length x Height
Area = 6.2m x 1.5m
Area = 9.3m2

We can now substitute our values into the forumla to solve for mass.
Weight = 9.3 x 0.04 x 7,850kg/m3 where 7,850kg/m3 is equal to the density of steel.
Weight = 2,952kg or 2.94 tonnes.

However, given the shape of the baseplate mounted to TES is not a perfect rectangle, we can reduce a further 5% from our total weight to account for areas where material should not exist.
5% of 2.94 is 0.14
2.94 - 0.14 = 2.8
Our total weight for one steel base plate mounted to TES is approximately 2.8t

Each side of TES has a baseplate. There are two base plates so we multiply the 2.8 by 2 to get 5.6, making the total weight of our steel baseplates on Challenger 2 OES and TES 5.6T

SECTION 3. MINE PROTECTION.

Screenshot 2024-01-19 185515

The Challenger 2 TES and OES mount protective armor under the crew compartment to defend against IEDs and anti-tank mines.
The total size of the mine plate can be seen taking up roughly 2/3 of the tanks total width.
2/3 of 3.5 (the width of the Challenger 2 as established in Section 1) is 2.33 meters.


It can be seen encompassing the same length as the base plate, therefore it is assigned the same length established in Section 2 of 6.3 meters.
The dimensions for our mine protection is therefore 6.3 meters long, 2.33 meters wide and 20 mm thick.
Please note that while this is Rolled Homogenous Armor, the density of the material appears to not change from that of steel, so the approximation will be using 7,850kg/m3 as a baseline.

Using the formula from Section 2, we obtain the following:
Area = 6.2 x 2.33
Area = 14.486 m^2
Weight = 14.486m^2 x 0.02 x 7850kg/m^3
Weight = 2,278.46kg or 2.27t for the mine protective underplate.

Section 4: Dual 40mm spaced armor

In all TES and OES vehicle modifications, there are two 40mm thick steel plates per side, mounted to the sides.
The plates height are almost exactly 1/4 the height of the baseplate.
Screenshot 2024-01-19 185724

1/4 of 1.5 (the height obtained in Section 2) is 0.375.
The length is the same as the base plate at 6.3m
The width is 40mm per plate, of which there are two per side.
Using the same formula, we can solve for total mass…
Area = 6.3m x 0.375m
Area = 2.3625m2

Weight = 2.3625m2x0.04x7,850kg/m3
Weight = 742.6KG or 0.74 tons
This is just the weight of one individual plate. There are four, per TES/OES.
0.74 x 4 is 2.96

We can reduce this value by roughly 5% again, as the bottom slopes towards the front saving us material.
20% off the total number (5% per block) is 2.96 - 0.59 = 2.36t for the bars at the bottom of the plate.

In total, with the base plate, double stack side armor and mine protection, our approximated weight is:
2.36 + 2.27 + 5.6
= 10.23

The TES modification weighs 12.3T, therefore: 12.3 - 10.23 = 2.07
This leaves you with 2.07T of weight to be added in the form of the LFP addon armor, Cage/Bar armor, Radio equipment, ASPRO-HMT and ECM.

SECTION 5: ALUMINIUM THEORY

To streamline this section, the exact same dimensions and formulae as previously used for steel will be used, however the density of steel will be replaced with 2810kg/cm^3, the density of Aluminium Alloy 7075 as pure aluminium would not be used.

Running the formula again, but with this density change provides you with 1045.32KG or 1.04t x 2 = 2.08t total for the base plates.
Mine protection remains unchanged, as does the 40mm plates at the bottom.
This provides us the values:
2.08 + 2.36 + 2.27 which is 6.71t total if using Aluminium base plates.

CONCLUSIONS

The Challenger 2 TES package is known to be 12.3T as represented in War Thunder. When applying our formulae to the baseplates and using steel as our material, we are provided with a value that closely matches our expectations of the weight of the TES package if certain elements are removed such as the ECM, Radio, Slat Armor, Frontal Plate Protection and ASPRO-HMT. There is 2.07T left when considering the material as steel, for the remaining equipment to be installed, which when added, would be in the approximate range of the 12.3T target.

When considering the Aluminium theory, however, we are left with close to 7T of weight to account for. We know from the March 2010 addition of Armor & Mobility that ASPRO-HMT does not weigh much:
image
And therefore the slat armor, ECM, LFP protection and radio would need to make up the weight of almost 7 tons which is unlikely.

Therefore, it is my belief that Steel closely matches the weight, expected of the plates and is the likely material used on Challenger 2 TES.

Thank you.

17 Likes

I still think your over estimating the width of the mine protection is about 1/2 of the total width


So i think

Possibly. I took this into account when using my formula as it is an approximation, not an exact. It’s roughly between 1/3 and 2/3. I have rounded this up to error as my formula does not account for the extra material that comes up from the plate, just a flat surface. The overapproximation accounts for the added material that makes the mine protection plate’s walls.

1 Like

To me this is too low.

Depending on how effective a “shot” is, that is extremely cheap.

I agree, the aspro tiles being 40kg is about 1t total. LFP block is probably 1t considering the old ERA LFP weighed over 1t

Remember that this is a rough approximation by creating a perfect rectangular object, and shaving off percentages of the objects calculated weight to simulate its non-rectangular shape and the materials savings that would incur.
The calculations aren’t designed to show how heavy the side plates are exactly, it is simply to provide a rough estimation on which value is the closest to our expected 12.3t mass of the TES package.
In no way am I saying it is 2.07T exactly.

The reasoning is that it’s more believable/realistic to have the kit weigh closer to 2.07T than compared to Aluminum which requires almost 7T of additional weight.

Steel is more reasonable and falls closer in line with our expected weight ranges.

The ASPRO-HMT bricks weigh 40KG each, there are 13 bricks per side, 26 total.
40 x 26 gives you 1040KG which is 1.04t
Assuming the frontal plate is also 1t, that leaves you with 300KG to install the rather lightweight slat armor, ECM and radio equipment.

I’ve given myself a half ton margin or error given I was not shaving off exact dimensions for the shapes, so ~800KG available to install everything. More than realistic.

Now compare this to Aluminium. You have 6.71t spare.
ASPRO-HMT is 1.04t
LFP is 1t
You are still left with approximately 4 Toyota Corollas in weight for a radio assembly, ECM, and slat armor.

No way.
The point of the document is to illustrate that steel is closer. Not that these are the exact values. Don’t get hung up on the actual numbers, they are ballpark figures to see which is closer to 12.3t

2 Likes

Appreciate your passion and dedication to the game and us as players. Glad you see you keep everything fair regardless of the nation.

4 Likes

Which I disagree with, 1T sounds too low

Remember that Legwolf calculations ignore all the other changes, like for example lighter drive wheels



I know the reduction of mass is not gigantic, just an example of omitted thing

1 Like

You’re getting hung up on exact values. This isn’t a matter of “this value is exactly 1t” or not.
it’s that the weight of the steel plates closer matches the expected weights of components than aluminium.

Unless you mean to suggest the LFP block weighs in excess of 3 tons, which I disagree with.

This reminded me of how I tried to prove to the developers that they did not take into account the penetration of the L23a1 projectile depending on the gun. I did the calculations based on the game data.

The L23a1 and L26 projectiles are on the (chelli mk3) L11A5 gun and on the (chelli 2) L30a1, L26 on the L30a1 penetrates 4.7% more. But why is the penetration of the L23a1 equally independent of the gun?

“” It is not a mistake, there are not enough documents confirming that this is the case"" :))))))))))))))